MANAGEMENT TEAM: BOVIS EUROPE
ARCHITECT: I.N.C. LTD
CONSULTANT: R.W. GREGORY / W T PARKER
QUANTITY SURVEYOR: SILK and FRAIZER
NATURE OF PROJECT: BUILDING SERVICES PROJECT
AVERAGE LABOUR STRENGTH: 25
CONTRACT PERIOD: DESIGN 12 WEEKS, CONSTRUCTION PERIOD 22 WEEKS
Project details:
WT Parker were commissioned to design all electrical and mechanical services for the above project work. It involved the preliminary re-routing of the 415V mains and public services to the final finishes of the new mall and entrance hall. Working closely with the centre's architectural practice, from the initial contract of £2 million W T Parker was awarded with further contracts to a total value of £6.5 million.
On Site Management
The site was autonomous from the Burton office and consisted of the following site team:
Contracts Director
Commercial Manager
Projects Manager
Mechanical Engineer
Site CAD Operator
2 Site Supervisors
45 Site Electricians
22 Mechanical Craftsmen